What needs to happen
Drag actions through the stages. Status updates flow to plant cards, MPR and system pages instantly.
Not started
20
A-100 · FB1
amberCrane #2 availability 82%, replace grab rope
Mechanical Supervisor · Due 2026-06-05
Availability risk · £7k
A-101 · FB1
amberSuperheater temp above corrosion-zone band
Plant Reliability Lead · Due 2026-06-05
Availability risk · £7k
A-103 · FB1
redBFP B oil sample overdue
Plant Reliability Lead · 1 day overdue
≈ 4 MW recoverable · £74k
A-104 · FB1
amberAux load drift +0.2 MW MTD
Electrical Lead · Due 2026-06-05
Availability risk · £7k
A-105 · FB1
amberID fan #1 vibration trending up
Mechanical Supervisor · Due 2026-06-05
Availability risk · £7k
A-106 · FB2
amberSuperheater temp above corrosion-zone band
Plant Reliability Lead · Due 2026-06-05
Availability risk · £7k
A-107 · FB2
amberAux load drift +0.2 MW MTD
Electrical Lead · Due 2026-06-05
Availability risk · £7k
A-109 · KEM
redReject rate trending up on tip floor
Mechanical Supervisor · 1 day overdue
~£29k/wk · £29k
A-110 · KEM
amberSuperheater temp above corrosion-zone band
Plant Reliability Lead · Due 2026-06-05
Availability risk · £7k
A-111 · KEM
amberVacuum / ACC fans, 2 offline since Mon
Plant Reliability Lead · Due 2026-06-05
≈ 4 MW recoverable · £73k
A-112 · KEM
amberAux load drift +0.2 MW MTD
Electrical Lead · Due 2026-06-05
Availability risk · £7k
A-113 · KEM
amberID fan #1 vibration trending up
Mechanical Supervisor · Due 2026-06-05
Availability risk · £7k
A-114 · PA
amberAux load drift +0.2 MW MTD
Electrical Lead · Due 2026-06-05
Availability risk · £8k
A-115 · SKL
amberCrane #2 availability 82%, replace grab rope
Mechanical Supervisor · Due 2026-06-05
Availability risk · £7k
A-117 · SKL
redBring forward UT inspection
Plant Reliability Lead · 1 day overdue
~£30k/wk · £30k
A-118 · SKL
amberVacuum / ACC fans, 2 offline since Mon
Plant Reliability Lead · Due 2026-06-05
≈ 4 MW recoverable · £74k
A-119 · SKL
amberBag-filter ΔP creep, pulse clean optimisation
Environmental Lead · Due 2026-06-05
Availability risk · £7k
A-120 · SKL
amberAux load drift +0.2 MW MTD
Electrical Lead · Due 2026-06-05
Availability risk · £7k
A-122 · SKL
redBearing temp +4 °C in 14d
Mechanical Supervisor · 1 day overdue
~£30k/wk · £30k
A-123 · KVL
amberVacuum / ACC fans, 2 offline since Mon
Plant Reliability Lead · Due 2026-06-05
≈ 4 MW recoverable · £74k
Underway
4
A-102 · FB1
redVacuum / ACC fans, 2 offline since Mon
Plant Reliability Lead · Due in 2 days
≈ 4 MW recoverable · £74k
A-108 · KEM
redCrane #2 availability 82%, replace grab rope
Mechanical Supervisor · Due in 2 days
~£29k/wk · £29k
A-116 · SKL
redSuperheater temp above corrosion-zone band
Plant Reliability Lead · Due in 2 days
~£30k/wk · £30k
A-121 · SKL
redID fan #1 vibration trending up
Mechanical Supervisor · Due in 2 days
~£30k/wk · £30k
Stuck
0
No actions
Done
0
No actions