Kemsley
1 area needs action, 1 action overdue.
AI Executive SummaryRefreshing…
Kemsley is needs attention, availability 92.4% vs 95% target, 1 area red and 4 amber.
Running well
- •Turbine is healthy and improving.
- •Combustion & flue-gas path is healthy.
- •Generator is healthy (watch the trend).
Worth watching
- •Boiler pressure parts is on the watchlist, confirm next-outage corrosion zone temperature band; bring forward ut inspection.
- •Water & steam cycle is on the watchlist, quarterly bfp efficiency check, sample within 4 weeks.
- •Electrical & control system is on the watchlist, define data feeds for hv/lv boards and grid connection, most kpis limited today.
- •Pumps, fans & rotating kit is on the watchlist, id fan #1 alignment check; trend bearing temp daily this week.
Needs action
- •Fuel handling needs action, Crane #2 availability 82%, replace grab rope (owner Mechanical Supervisor, Due in 2 days).
- •1 action overdue across the plant.
- •Behind plan this month by £27k on revenue.
Generated from sample data.
Available to run
92.4%
target 95%
Energy sent to grid
28.6 GWh
avg 42.5 of 46 MW
Revenue (indicative)
£3.08m
energy × indicative price
Behind plan
-£27k
year-end if trend holds -£338k
The four numbers that matter
Plant headline, streamed live.
Available to run
92.4%
Share of time the plant could generate.
Runs as expected
95.1%
How often it runs without unplanned trips.
Unplanned downtime
2.8%
Time lost to faults we didn't schedule.
Planned downtime
340hrs YTD
Time set aside for maintenance.
The 10 areas of the plant
Click any area to drill into its sub-KPIs.
Fuel Handling
redFuel Bunker Level
71%
Waste Crane 1 Status
96% avail
Waste Crane 2 Status
82% avail
+1 more KPIs →
Owner: Mechanical Supervisor
Boiler Pressure Parts
amberSteam/Feed Diff (Tube Leak)
0.4t/h
Useful Heat Output
92MWth
PSSR Systems
Not yet measured
+2 more KPIs →
Owner: Plant Reliability Lead
Turbine
greenVacuum
76mbar(a)
Gland Steam Status
1OK
Lube Oil System Status
1OK
+2 more KPIs →
Owner: Performance Engineer
WSC (Excluding Boiler)
amberFeedwater System Status
1OK
Main Condensate System Status
1OK
WTP Status
1OK
+5 more KPIs →
Owner: Plant Reliability Lead
Boiler Flue Gas Path / Combustion
greenFouling Diffs
1.42kPa
1st Pass Roof Temp
612°C
S/H Inlet Flue Gas Temp
720°C
+8 more KPIs →
Owner: Ops Shift Manager
Generator
greenExcitation Status
Not yet measured
PD Monitoring
12pC
Reactive Power / Excitation Status
4.2MVAr
+1 more KPIs →
Owner: Electrical Lead
FGT / Emissions / CEMS
greenLime Consumption
312kg/h
Carbon Consumption
42kg/h
Residue Recirculation (F1/F2)
0.78ratio
+6 more KPIs →
Owner: Environmental Lead
Electrical Power Systems / DCS
amberMain Transformer Status
1OK
HV/LV Transformers Status
Not yet measured
EDG Status
Not yet measured
+3 more KPIs →
Owner: Electrical Lead
Rotating Plant
amberCombustion Fans Status
1OK
ID Fan Status
5.8mm/s
Feedwater Pump Status
1OK
+4 more KPIs →
Owner: Mechanical Supervisor
Ash Systems / Bunker / Aux Plant
greenAsh Ext 1 Status
1OK
Ash Ext 2 Status
1OK
Ash Conveyors Status
1OK
+4 more KPIs →
Owner: Ops Shift Manager
Needs attention
Top risks right now, rotating every few seconds.
Timeline
What's been flagged, started, and resolved.
Recent events
10 entries
- 29 MayFlagID fan #1 vibration trending upPumps, fans & rotating kit · A-113 · Mechanical Supervisor
- 29 MayFlagAux load drift +0.2 MW MTDElectrical & control system · A-112 · Electrical Lead
- 29 MayFlagVacuum / ACC fans, 2 offline since MonWater & steam cycle · A-111 · Plant Reliability Lead
- 29 MayFlagSuperheater temp above corrosion-zone bandBoiler pressure parts · A-110 · Plant Reliability Lead
- 27 MayUnderwayWork started, Crane #2 availability 82%, replace grab ropeFuel handling · Mechanical Supervisor
- 23 MayFlagCrane #2 availability 82%, replace grab ropeFuel handling · A-108 · Mechanical Supervisor
- 20 MayFlagReject rate trending up on tip floorFuel handling · A-109 · Mechanical Supervisor
- 29 AprIncidentForced outage 14 hrs (BFP B trip)
- 17 AprIncidentBag filter ΔP alarm
- 3 AprIncidentCrane #1 outage 9 hrs