Enfinium

Parc Adfer

Running, 1 area to watch.

AI Executive SummaryRefreshing…

Parc Adfer is running but with items to watch, availability 97.2% vs 95% target, 0 areas red and 1 amber.

Running well

  • Plant is available to run 97.2% of the time, on or above the 95% target.
  • Fuel handling is healthy and improving.
  • Boiler pressure parts is healthy and improving.
  • Turbine is healthy and improving.

Worth watching

  • Electrical & control system is on the watchlist, define data feeds for hv/lv boards and grid connection, most kpis limited today.

Needs action

  • Behind plan this month by £100k on revenue.
Generated from sample data.
Available to run
97.2%
target 95%
Energy sent to grid
15.7 GWh
avg 23.3 of 24 MW
Revenue (indicative)
£1.75m
energy × indicative price
Behind plan
-£100k
year-end if trend holds -£1.26m

The four numbers that matter

Plant headline, streamed live.

Available to run
97.2%
Share of time the plant could generate.
Runs as expected
98.4%
How often it runs without unplanned trips.
Unplanned downtime
0.9%
Time lost to faults we didn't schedule.
Planned downtime
196hrs YTD
Time set aside for maintenance.

The 10 areas of the plant

Click any area to drill into its sub-KPIs.

Timeline

What's been flagged, started, and resolved.

Recent events
2 entries
  1. 29 May
    Flag
    Aux load drift +0.2 MW MTD
    Electrical & control system · A-114 · Electrical Lead
  2. 10 Apr
    Incident
    PI server failover, no plant impact