Enfinium

Skelton Grange

2 areas need action, 2 actions overdue.

AI Executive SummaryRefreshing…

Skelton Grange is needs attention, availability 89.7% vs 94% target, 2 areas red and 4 amber.

Running well

  • Turbine is healthy.
  • Combustion & flue-gas path is healthy (watch the trend).
  • Generator is healthy (watch the trend).

Worth watching

  • Fuel handling is on the watchlist, crane #2 grab-rope inspection; pull spares forward into the kit.
  • Water & steam cycle is on the watchlist, quarterly bfp efficiency check, sample within 4 weeks.
  • Emissions & flue-gas cleaning is on the watchlist, schedule pulse-clean optimisation on bag filters, δp creeping.
  • Electrical & control system is on the watchlist, define data feeds for hv/lv boards and grid connection, most kpis limited today.

Needs action

  • Boiler pressure parts needs action, Superheater temp above corrosion-zone band (owner Plant Reliability Lead, Due in 2 days).
  • Pumps, fans & rotating kit needs action, ID fan #1 vibration trending up (owner Mechanical Supervisor, Due in 2 days).
  • 2 actions overdue across the plant.
  • Behind plan this month by £116k on revenue.
Generated from sample data.
Available to run
89.7%
target 94%
Energy sent to grid
29.6 GWh
avg 44.0 of 49 MW
Revenue (indicative)
£3.25m
energy × indicative price
Behind plan
-£116k
year-end if trend holds -£1.46m

The four numbers that matter

Plant headline, streamed live.

Available to run
89.7%
Share of time the plant could generate.
Runs as expected
93.8%
How often it runs without unplanned trips.
Unplanned downtime
3.4%
Time lost to faults we didn't schedule.
Planned downtime
420hrs YTD
Time set aside for maintenance.

The 10 areas of the plant

Click any area to drill into its sub-KPIs.

Needs attention

Top risks right now, rotating every few seconds.

Timeline

What's been flagged, started, and resolved.